Rollout

§22InformativeDraft 2.3Latest draft

This section is informative.

Nine studies from the research review, plus a benchmark pilot added in this draft, now sit inside the phase plan, and three of them must report before any client-facing use: the estimand round trip, the acceptance-bar benchmark and the agent evaluation harness.

Pre-rollout studies

#StudyPass criterionBlocks
1Estimand round trip: Meridian, Robyn, PyMC-Marketing and in-house frameworks on shared simulated truth, exchanged through UMPDeclared-equivalent estimands agree within Monte Carlo error; every mismatch is caught, aligned and labelled, and each widened interval covers the truth whenever one of its registered alternatives holdsExit of P0
2Acceptance-bar benchmark: endogenous-spend simulator plus AMSS-style scenarios, MTM as negative controlPositive control passes, MTM fails; pass marks calibrated and pre-registeredCertification (P3), and pilot status for any new family
3Calibration bake-off: R1, R2 with interval lift, R4 reweighting, on known truth, including partial cuts and adstock tailsCoverage within 5 points of nominal; PSIS rule catches every collapseInterval lift and R5 leaving pilot (P2)
4Interval-lift write-up crediting PyMC-MarketingInternal paper with signed, adstock-aware, two-arm resultsPublication of the extension
5Agent evaluation harness: golden set, citation scoring, injection red teamSection 17 pass marksNewton read-only pilot (P1) and every Newton release
6Historical placebo study: TBR, Trimmed Match and augmented SC on our own null windowsMeasured false-positive rates and design effects replace defaultsDefault design parameters (P2)
7Decision-record back-test of past reallocationsOptimiser’s-curse shrinkage estimated by channelCurse adjustment leaving provisional (P3)
8Audit-log hardening: Merkle log with RFC 3161 and external anchoring, rotation and erasure drillsTamper and forgery fixtures detected; erasure leaves proofs validSealing decisions in production (P1)
9Governance pilot metrics for one quarterCycle time, bypass rate and override frequency baselinedScaling beyond the pilot account (P4)
10Benchmark pilot: calibrates the section 25 constants (SE multipliers, ageing rate and floor, tau floor, contributor floor, prior weights, gap-screen r values, epsilon budget)Each proposed constant replaced by a calibrated value or kept with a recorded reasonBenchmark values leaving proposed (P4)

Phases and exit gates

  1. P0
  2. P1
  3. P2
  4. P3
  5. P4
  6. Not tied to a phase

Three studies must report before any client-facing use: the estimand round trip (1), the acceptance-bar benchmark (2) and the agent evaluation harness (5). They are marked client-facing above.

Phase dates overlap where workstreams run in parallel. A phase closes only when its gate evidence is filed as an artifact.

Figure 22.1 Five phases and the nine studies that gate them. Each study sits under the phase milestone it blocks, as listed in the pre-rollout studies table. Pick a study to read its pass criterion, or show the three that must report before any client-facing use.

Phase dates overlap where workstreams run in parallel; a phase closes only when its gate evidence is filed as an artifact.

What we need. One to two platform engineers for the core and gates; data engineering time for intake parsers; in-house modelling time for interval lift and geo-set lift tests; a measurement lead to own the estimand registry and studies 1 to 3; an agent host steward; a key custodian; named reviewers and a planning champion on the pilot account.